Skip to content
Counterweights, Stacker_____________________Burner display_____________________Electric Stacker_____________________Nsvzkary_____________________UPS boards

News category: ‘Fabricating Workshop’

Start of Flooring in Fabricating Workshop

Concrete floor of Fabricating workshop began on 2014/04/25.

Starting the installation of structure fabrication workshop.

Installation of structure fabrication workshop will start on 2014.03.06.

Reinforcement activities of Sand belast & painting

Reinforcement of foundation Sand belast & painting began on 26/02/2014.

you can see the latest pictures by clicking here.

Starting the concreting of Workshop

accomplishment of concreting the South foundation Fabricating workshop; using up to 35 cubic meter concrete, on 8/2/2014 ..
you can see the latest pictures by clicking here.

Reinforcement activities Fabricating workshop

Reinforcement foundation western part of the workshop was start on 14/1/2014.
you can see the latest pictures by clicking here.

Lean Concrete activity of fabrication workshop has been started

Lean Concrete foundation of fabrication workshop started on 14/1/2014.

Begin of fabricating workshop executive activities

Begin of Fabricating workshop Excavation Activities on 02/01/2014.

DSC09948