News category: ‘Green Pelletizing’
Align the top of the disk mounting structure
Since the beginning of March 94, installation disc in the top level structure Green construction began.
The beginning of the Civil conveyor CV04
The date 94/07/19 by sending drawings to the job site excavation foundation conveyor CV04 hall began mixing the raw pellets.
Foundation concreting of Axis 7 Green Pelletizing
Foundation Concreting of 7th base F-2 with volume of 235 cubic meters was done on 22/12/2013 , thus the concreting in foundation is completed except holded parts . Photos below show the concreting of mentioned foundation:
Foundation concreting of axis 8 Green Pelletizing
Concreting of F-6 foundation axis 8 was conducted on 19/12/2013 to the volume of 170 cubic meters. Pictures below show the concreting of the foundation:
Foundation concreting of axis 6 Green Pelletizing
Concreting of F-2 foundation axis 6 was conducted on 17/12/2013 to the volume of 243 cubic meters. Pictures below show the concreted foundation.
Foundation concreting of axis 5 Green Pelletizing
Concreting of F-2 foundation axis 5 was conducted on 12/12/2013 to the volume of 240 cubic meters.
Foundation Concreting of axis 4 Green Pelletizing
Concreting of F2-B foundation, axis 5 was conducted on 9/12/2013 to the volume of 171 cubic meters.
Foundation Concreting of axis 3 Green Pelletizing
Concreting of F2A foundation of axis 3 was conducted on 6/12/2013 to the volume of 138 cubic meters.
Start of the main concreting , axis 1 & 2 Green Pelletizing
The first main concreting of foundation of this department in axis 1 and 2 with the volume of 98 cubic meters was conducted successfully on 30/11/2013.