News category: ‘Indurating Building’
Main concrete of Indurating Building part 2
Part 2 of Indurating Building has been started with 85 cubic meter on 2014/04/29.
Start of construction part 2 Indurating foundation.
Reinforcement Part 2 from 2014/04/19 and formworking begin was date 2014/04/25..
Main concrete of Indurating Building part 3
Part 3 of Indurating Building has been started with 200 cubic meter on 10/04/2014.
Part 3 of Indurating Building
Lean Concrete of Part 3 with 24 cubic meters done on 13/03/2014.
Concreting Axis 130 and 140 of Indurating Building
accomplishment of concreting the Axis 130 and 140 foundations; using up to 180 cubic meter concrete, on 23/1/2014 ..
Concreting Axis 110 and 120 of Indurating Building
accomplishment of concreting the Axis 110 and 120 foundations; using up to 190 cubic meter concrete, on 20/1/2014 .
Concrete axis 90&100 Indurating Building
concrete foundation axis 90 and 100 amounts to 175 cubic meters was conducted on 17/1/2014.
Start of concrete activities Indurating Building
Concrete foundation axis 70 and 80 on 14/1/2014 amounts to 170 cubic meters.
Reinforcement activities Indurating Building Structures
Lean Concrete and Reinforcement have been started on 4/1/2014 and 7/1/2014.