Reinforcement activities of Sand belast & painting

Reinforcement of foundation Sand belast & painting began on 26/02/2014.

you can see the latest pictures by clicking here.

Starting the concreting of Workshop

accomplishment of concreting the South foundation Fabricating workshop; using up to 35 cubic meter concrete, on 8/2/2014 ..
you can see the latest pictures by clicking here.

Start sandblast & painting workshop operation

sandblast & painting workshop Excavation began on 18/1/2014.
you can see the latest pictures by clicking here.

Reinforcement activities Fabricating workshop

Reinforcement foundation western part of the workshop was start on 14/1/2014.
you can see the latest pictures by clicking here.

Lean Concrete activity of fabrication workshop has been started

Lean Concrete foundation of fabrication workshop started on 14/1/2014.

Begin of fabricating workshop executive activities

Begin of Fabricating workshop Excavation Activities on 02/01/2014.