News category: ‘Construction’

The second support installation of concentrate mixture Hall

Second support is the concentrate mixing Hall on 93/10/04 was installedDSCF4573

Installation of the first pelletizing equipment

Support the incorporation of the concentrate Hall on 93/09/24 The equipment was installed and launched Project.

DSCF4311

Start installation of structure Stage 2 Green

Columns and beams mounted on the stage 2 Green 1393/09/11 was.

Restart pelletizing project engineering activities by 1393/06/11

During meetings last week with the Ural Mkhanvbr companies and Turks(Technologists pelletizing project)In Russia was held and attended by the project manager and director of engineering, basic engineering of the project was decided that the remaining activities in accordance with the approved schedule will resume.

Continue running the workshop roof colored

Install roof of the workshop are to be painted and pre-assembled crane is also beginning.

 

The mounting structure kiln structures

From 93/05/28 installed and running quickly is to start the furnace structure.

Ready to equip new workers' dormitories

Since the beginning of September, 93 new workers' hostel with capacity for 120 people and equipped to exploit the.

Installation of structure Indurating Building

اInstallation of structure Indurating Building has been started on 2014/08/01.

Installation of structure Green pelletizing

Installation of structure Green pelletizing has been started on 2014/06/06.