The second support installation of concentrate mixture Hall
Second support is the concentrate mixing Hall on 93/10/04 was installed
Installation of the first pelletizing equipment
Support the incorporation of the concentrate Hall on 93/09/24 The equipment was installed and launched Project.
Start installation of structure Stage 2 Green
Columns and beams mounted on the stage 2 Green 1393/09/11 was.
Restart pelletizing project engineering activities by 1393/06/11
During meetings last week with the Ural Mkhanvbr companies and Turks(Technologists pelletizing project)In Russia was held and attended by the project manager and director of engineering, basic engineering of the project was decided that the remaining activities in accordance with the approved schedule will resume.
Continue running the workshop roof colored
Install roof of the workshop are to be painted and pre-assembled crane is also beginning.
Ready to equip new workers' dormitories
Since the beginning of September, 93 new workers' hostel with capacity for 120 people and equipped to exploit the.
Installation of structure Green pelletizing
Installation of structure Green pelletizing has been started on 2014/06/06.