News category: ‘Pelletizing IMIDRO’
The second support installation of concentrate mixture Hall
Second support is the concentrate mixing Hall on 93/10/04 was installed
Installation of the first pelletizing equipment
Support the incorporation of the concentrate Hall on 93/09/24 The equipment was installed and launched Project.
Start installation of structure Stage 2 Green
Columns and beams mounted on the stage 2 Green 1393/09/11 was.
Blasting activities
Concentrated blast from the date of the 1393/06/22 was.
you can see the latest pictures by clicking here.
Restart pelletizing project engineering activities by 1393/06/11
During meetings last week with the Ural Mkhanvbr companies and Turks(Technologists pelletizing project)In Russia was held and attended by the project manager and director of engineering, basic engineering of the project was decided that the remaining activities in accordance with the approved schedule will resume.
Concentrate on making Bynhay
From 93/05/15 Construction work started Bynhay concentrate on cutting Kalktyng Hopper continued to work.
Start of construction equipment in the workshop Sangan
From 93/05/15 work began on the construction of the equipment in the workshop Sangan's manufacturing capacity will gradually increase.
Continue running the workshop roof colored
Install roof of the workshop are to be painted and pre-assembled crane is also beginning.