The second support installation of concentrate mixture Hall

Second support is the concentrate mixing Hall on 93/10/04 was installedDSCF4573

Installation of the first pelletizing equipment

Support the incorporation of the concentrate Hall on 93/09/24 The equipment was installed and launched Project.

DSCF4311

Start installation of structure Stage 2 Green

Columns and beams mounted on the stage 2 Green 1393/09/11 was.

Blasting activities

Concentrated blast from the date of the 1393/06/22 was.

you can see the latest pictures by clicking here.

 

Restart pelletizing project engineering activities by 1393/06/11

During meetings last week with the Ural Mkhanvbr companies and Turks(Technologists pelletizing project)In Russia was held and attended by the project manager and director of engineering, basic engineering of the project was decided that the remaining activities in accordance with the approved schedule will resume.

Concentrate on making Bynhay

From 93/05/15 Construction work started Bynhay concentrate on cutting Kalktyng Hopper continued to work.

Start of construction equipment in the workshop Sangan

From 93/05/15 work began on the construction of the equipment in the workshop Sangan's manufacturing capacity will gradually increase.

 

Continue running the workshop roof colored

Install roof of the workshop are to be painted and pre-assembled crane is also beginning.

 

The mounting structure kiln structures

From 93/05/28 installed and running quickly is to start the furnace structure.