News category: ‘Civil’

Concreting Axis 110 and 120 of Indurating Building

accomplishment of concreting the Axis 110 and 120 foundations; using up to 190 cubic meter concrete, on 20/1/2014 .

you can see the latest pictures by clicking here.

Concrete axis 90&100 Indurating Building

concrete foundation axis 90 and 100 amounts to 175 cubic meters was conducted on 17/1/2014.

Start of concrete activities Indurating Building

Concrete foundation axis 70 and 80 on 14/1/2014 amounts to 170 cubic meters.

you can see the latest pictures by clicking here.

Reinforcement activities Indurating Building Structures

Lean Concrete and Reinforcement have been started on 4/1/2014 and 7/1/2014.

DSC09747

 

Begin of Indurating Building executive activities

According to reception of foundation plots of this building from Tehran office on 11/12/2013, the prerequisite activities carried out on the same date.. It is notabe that foundation excavation was already completed in Site Leveling procedure. From the mentioned date, the surveying tasks continued and each place that required excavation or embankment was corrected.

Foundation concreting of Axis 7 Green Pelletizing

Foundation Concreting of 7th base F-2 with volume of 235 cubic meters was done on 22/12/2013 , thus the concreting in foundation is completed except holded parts . Photos below show the concreting of mentioned foundation:

DSC09148DSC09143

FC Drawings Announcement of the Indurating building foundation on 11/12/2013

The first part of Drawing of the Indurating building foundation based on transmittal number AZT/PRJ/P/T0060 , on 11/12/2013 was sent to site from Tehran office to initiate enforcement actions.

Foundation concreting of axis 8 Green Pelletizing

Concreting of F-6 foundation axis 8 was conducted on 19/12/2013 to the volume of 170 cubic meters. Pictures below show the concreting of the foundation:

DSC08836 DSC08836 DSC08836

Foundation concreting of axis 6 Green Pelletizing

Concreting of F-2 foundation axis 6 was conducted on 17/12/2013 to the volume of 243 cubic meters. Pictures below show the concreted foundation.

DSC08836 DSC08836 DSC08836