News category: ‘Civil’
Foundation concreting of axis 5 Green Pelletizing
Concreting of F-2 foundation axis 5 was conducted on 12/12/2013 to the volume of 240 cubic meters.
Foundation Concreting of axis 4 Green Pelletizing
Concreting of F2-B foundation, axis 5 was conducted on 9/12/2013 to the volume of 171 cubic meters.
Foundation Concreting of axis 3 Green Pelletizing
Concreting of F2A foundation of axis 3 was conducted on 6/12/2013 to the volume of 138 cubic meters.
Start of the main concreting , axis 1 & 2 Green Pelletizing
The first main concreting of foundation of this department in axis 1 and 2 with the volume of 98 cubic meters was conducted successfully on 30/11/2013.
concreting plan of green pelletizing department
The main concreting of foundation will start on 30/11/2013.
Mixing Hall padding
Padding works were completed on 28/11/2013.